1. Brick walls are measured in sq. m if the thickness of the wall is

Correct : A. 10 cm

2. The brick work is not measured in cu m in case of

Correct : D. half brick wall

3. The following item of earth work is not measured separately.

Correct : B. site clearance

4. The measurement is not made in square meters in case of

Correct : D. r.c. chhajja

5. Pick up the incorrect statement from the following:

Correct : C. cubic contents are measured to the nearest 0.1 cum

6. The item of steel work which is measured in sq.m, is

Correct : A. collapsible gates

7. The damp proof course (D.P.C.) is measured in

Correct : B. sq. m

8. For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is

Correct : B. 0.94 m3

9. According to ISI method of measurement, the order of the sequence is

Correct : A. length, breadth, height

10. Carpet area does not include the area of

Correct : B. bath room and lavatory

11. The item of the brick structure measured in sq.m, is

Correct : B. broken glass coping

12. The 'centre line method' is specially adopted for estimating

Correct : B. rectangular buildings

13. The order of Taking dimensions is

Correct : A. length, breadth, height

14. Pick up the item of work not included in the plinth area estimate

Correct : D. courtyard area

15. If the formation level of a highway has a uniform gradient for a particular length, and the ground is also having a longitudinal slope, the earthwork may be calculated by

Correct : A. mid-section formula

16. In the mid-section formula

Correct : A. the mean depth is the average of depths of two consecutive sections

17. The correct Prismoidal formula for volume is

Correct : B. d/3 [first area + last area + 4 Ʃ even area + 2 Ʃ odd areas]