Cost Management | Set 2

1. Public utility undertakings must invariably adopt---------

Correct : D. Multiple costing

2. Kerala Electricity Board must make use of-----------

Correct : A. Single or unit costing

3. The method of costing used in case of a gas company is termed as---------

Correct : C. Operating costing

4. Mines `A’ and `B’ are at a distance of 10 kms and 15 kms from the factory. The cost per tonne-km in case of mine A is Rs. 3 while it is R. 2.5 in case of mine B. The factory should procure coal from------------

Correct : A. Mine A only

5. In case of steam company, the cost per unit is calculated on the basis of---------

Correct : A. Total quantity of lbs. produced

6. Calendar variance is the sub variance of ---------------

Correct : C. Fixed Overhead variances

7. Which of the following is /are support activity in Value Chain Analysis?

Correct : D. All of these.

8. Which of the following is /are primary activity in Value Chain Analysis?

Correct : D. Service

9. ----------- variance is always adverse.

Correct : C. Idle time variance

10. ----------- are those products which are manufactured in different varieties by the same industry.

Correct : C. Co-products

11. ---------- means ‘Change for better’.

Correct : B. Kaizen

12. Lean manufacturing can be achieved by using-----------

Correct : C. Just in Time

13. ----------is the cost attribution to the cost unit on the basis of benefits received from indirect activities.

Correct : A. Activity based costing

14. Traditional absorption costing is ----------

Correct : B. Volume based

15. In Activity based costing, importance given to-----------

Correct : C. Overhead

16. ------------ is the item of product. Job, process or customer for which cost are to be determined.

Correct : B. Cost object

17. ‘Cost of Procurement’ is an example of---------------

Correct : C. Cost pool

18. ----------- in Activity Based Costing is like ‘cost centre’ in traditional costing.

Correct : C. Cost pool

19. ---------- cost is also known as hypothetical or notional cost.

Correct : C. Imputed cost