Quiznetik
Operations Management and Strategic Management | Set 1
1. Out of the following trends in production/operations management, which one is sometimes called as agile manufacturing?
A. Re-engineering
B. Supply-Chain Management
C. Lean Production
D. Flexibility
Correct : D. Flexibility
2. Out of the following factors that are affecting Capacity Planning, which one is Less Controllable one?
A. Machine break-downs
B. Amount of labour employed
C. Facilities installed
D. Shifts of work per day
Correct : A. Machine break-downs
3. Which of the following stages of Product Life Cycle does attribute beginning of substantial increase in Sales and Profits?
A. Introduction
B. Growth
C. Maturity
D. Decline
Correct : B. Growth
4. Which one is NOT an index of Productivity?
A. Man-hour output
B. Productivity ratio
C. TQM
D. Use of Financial Ratios
Correct : C. TQM
5. The time by which an activity can be rescheduled without affecting the other activities - preceding or succeeding is called as
A. Slack
B. Independent Float
C. Free Float
D. Total Float
Correct : B. Independent Float
6. Reliability and per unit cost of which of the following spares are less?
A. Regular spares
B. Insurance spares
C. Capital spares
D. Rotable spares
Correct : A. Regular spares
7. The lead-time is the time:
A. To place holders for materials
B. Time of receiving materials
C. Time between receipt of material and using materials,
D. Time between placing the order and receiving the materials
Correct : D. Time between placing the order and receiving the materials
8. The method used in scheduling a project is:
A. A schedule of break-down of orders
B. Outline master programme
C. PERT & CPM
D. Schedule for large and integrated work
Correct : C. PERT & CPM
9. MRP stands for:
A. Material requirement planning
B. Material reordering planning
C. Material requisition procedure
D. Material recording procedure
Correct : A. Material requirement planning
10. One of the important charts used in programme control is:
A. Material chart
B. Gantt chart
C. Route chart
D. Inspection chart
Correct : B. Gantt chart
11. Variety reduction is generally known as:
A. Less varieties
B. Simplification
C. Reduced varieties
D. None of the above
Correct : B. Simplification
12. Conversion of inputs into outputs is known as:
A. Application of technology
B. operations management
C. Manufacturing products
D. product
Correct : C. Manufacturing products
13. Number of product varieties that can be manufactured in Mass production is:
A. One only
B. Two only
C. Few varieties in large volumes
D. Large varieties in small volumes
Correct : C. Few varieties in large volumes
14. Routing and Scheduling becomes relatively complicated in
A. Job production
B. Batch production
C. Flow production
D. Mass production
Correct : B. Batch production
15. JIT stands for
A. Just in time purchase
B. Just in time production
C. Just in time use of materials
D. Just in time order the material
Correct : B. Just in time production
16. The first stage in production planning is:
A. Process planning
B. Factory planning
C. Operation planning
D. Layout planning
Correct : B. Factory planning
17. Scheduling deals with:
A. Number of jobs to be done on a machine
B. Number of machine tools used to do a job
C. Different materials used in the product
D. Fixing up starting and finishing times of each operation in doing a job
Correct : D. Fixing up starting and finishing times of each operation in doing a job
18. Example of production by disintegration is:
A. Automobile
B. Locomotive
C. Crude oil
D. Mineral water.
Correct : C. Crude oil
19. Fixing Flow lines in production is known as :
A. Scheduling
B. Loading
C. Planning
D. Routing
Correct : D. Routing
20. The material handling cost per unit of product in continuous production is:
A. Highest compared to other systems
B. Lower than other systems
C. Negligible
D. Cannot say.
Correct : B. Lower than other systems
21. (Total station time/Cycle time x Number of work stations) x 100 is known as:
A. Line Efficiency
B. Line smoothness
C. Balance delay of line
D. Station efficiency
Correct : A. Line Efficiency
22. Tempering is a process of:
A. Joining
B. Heat Treatment
C. Surface Treatment
D. Forming
Correct : B. Heat Treatment
23. For production planning:
A. Short term forecasting is useful
B. Medium term forecasting is useful
C. Long term forecasting is useful
D. Forecasting is not useful.
Correct : A. Short term forecasting is useful
24. Scheduling shows:
A. Total cost of production
B. Total material cost
C. Which resource should do which job and when
D. The flow line of materials
Correct : C. Which resource should do which job and when
25. Linear Programming is a technique used for determining:
A. Production Programme
B. Plant Layout
C. Product Mix
D. Manufacturing Sequence.
Correct : C. Product Mix
26. The effective capacity is NOT influenced by which of the following factors:
A. Forecasts of demand
B. Plant and labour efficiency
C. Subcontracting
D. None of the above
Correct : D. None of the above
27. Key aspects in process strategy does NOT include which of the following:
A. Make or buy decisions
B. Capital intensity
C. Process flexibility
D. Packaging
Correct : D. Packaging
28. The example of worker involvement, as a recent trend in production/operations management is
A. SCM
B. Just-in-Time
C. Quality Circle
D. MRP
Correct : C. Quality Circle
29. Production planning in the intermediate range of time is termed as
A. Production planning.
B. Long range production planning.
C. Scheduling.
D. Aggregate planning.
Correct : D. Aggregate planning.
30. Preventive maintenance is useful in reducing
A. Inspection Cost
B. Cost of premature replacement
C. Shutdown Cost
D. Set-up Cost of machine
Correct : C. Shutdown Cost
31. Which one of the following standards is associated with the "Quality Assurance in Production and Installation"?
A. ISO 9001
B. ISO 9002
C. ISO 9003
D. ISO 9004
Correct : B. ISO 9002
32. Number of product varieties that can be manufactured in Job production is:
A. Limited to one or two
B. Large varieties of products
C. One only
D. None of the above.
Correct : B. Large varieties of products
33. In general number of product varieties that can be manufactured in Flow production is:
A. One only
B. Ten to twenty varieties
C. Large varieties
D. Five only.
Correct : A. One only
34. Generally the size of the order for production in Job production is:
A. Small
B. Large
C. Medium
D. Very large.
Correct : A. Small
35. Generally in continuous production the production is carried out to:
A. Customer’s order,
B. Government orders only
C. For stock and supply
D. Few rich customers.
Correct : C. For stock and supply
36. The starting point of Production cycle is:
A. Product design
B. Production Planning,
C. Routing
D. Market research.
Correct : D. Market research.
37. Preferred numbers are used to:
A. To determine the number of varieties that are to be manufactured
B. To the test the design of the product
C. To ascertain the quality level of the product
D. To evaluate the production cost.
Correct : A. To determine the number of varieties that are to be manufactured
38. The act of assessing the future and make provisions for it is known as
A. Planning
B. Forecasting
C. Assessment
D. Scheduling.
Correct : B. Forecasting
39. For a marketing manager, the sales forecast is:
A. Estimate of the amount of unit sales or a specified future period
B. Arranging the sales men to different segments of the market
C. To distribute the goods through transport to satisfy the market demand
D. To plan the sales methods.
Correct : A. Estimate of the amount of unit sales or a specified future period
40. The time horizon selected for forecasting depends on:
A. The salability of the product
B. The selling capacity of Salesman
C. Purpose for which forecast is made
D. Time required for production cycle
Correct : C. Purpose for which forecast is made
41. In general, medium range forecasting period will be approximately:
A. 5 to 10 Years
B. 2 to 3 days
C. 3 to 6 months
D. 10 to 20 years
Correct : C. 3 to 6 months
42. The range of Long range forecasting period may be approximately:
A. 1 to 2 weeks
B. 2 to 3 months
C. 1 year
D. above 5 years
Correct : D. above 5 years
43. To plan for future man power requirement:
A. Short term forecasting is used
B. Long range forecasting is used
C. Medium range forecasting is used
D. There is no need to use forecasting, as future is uncertain.
Correct : B. Long range forecasting is used
44. Long range forecasting is useful in:
A. Plan for Research and Development
B. To Schedule jobs in Job production
C. In purchasing the material to meet the present production demand
D. To assess manpower required in the coming month.
Correct : A. Plan for Research and Development
45. Medium range forecasting is useful in:
A. To assess the loading capacity of the machine
B. To purchase a materials for next month
C. To plan for-capacity adjustments
D. To decide whether to receive production orders or not.
Correct : C. To plan for-capacity adjustments
46. To decide work load for men and machines:
A. Medium range forecasting is used
B. Short term forecasting is used
C. Long range forecasting is used
D. A combination of long range and medium range forecasting is used.
Correct : B. Short term forecasting is used
47. Important factor in forecasting production is:
A. Environmental changes
B. Available capacity of machines
C. Disposable income of the consumer
D. Changes in the preference of the consumer.
Correct : B. Available capacity of machines
48. Application of technology or process to the raw material to add use value is known as:
A. Product
B. Production
C. Application of technology
D. Combination of technology and process.
Correct : B. Production
49. In Production by disintegration the material undergoes:
A. Change in economic value only
B. Change in physical and chemical characteristics
C. Change in technology only
D. None of the above.
Correct : B. Change in physical and chemical characteristics
50. In Production by service, the product undergoes the changes in:
A. Shape and size of the surface
B. Shape of the surface only
C. Size of the surface only
D. Chemical and Mechanical properties.
Correct : D. Chemical and Mechanical properties.
51. Use of any process or procedure designed to transform a set of input elements into a set of output elements is known as:
A. Transformation process
B. Transformation of input to output
C. Production
D. Technology change
Correct : C. Production
52. Conversion of inputs into outputs is known as:
A. Application of technology
B. Operations management
C. Manufacturing products
D. Product
Correct : B. Operations management
53. The desired objective of Production and Operations Management is:
A. Use cheap machinery to produce
B. To train unskilled workers to manufacture goods perfectly
C. Optimal utilisation of available resources
D. To earn good profits.
Correct : C. Optimal utilisation of available resources
54. The scope of Production Planning and Control is:
A. Limited to Production of products only
B. Limited to production of services only
C. Limited to production of services and products only
D. Unlimited, can be applied to any type of activity.
Correct : D. Unlimited, can be applied to any type of activity.
55. Manufacturing system often produces:
A. Standardised products
B. Standardised products in large volumes
C. Substandardproducts in large volumes
D. Products and services in limited volume.
Correct : A. Standardised products
56. The difference between product system and project system is:
A. Project system the equipment and machinery are fixed where as in product system they are movable
B. In Product system the machinery and equipment are fixed and in project system they are not fixed
C. Project system produces only standardized products and product system produces only unstandardised products
D. Products cannot be stocked whereas projects can be stocked.
Correct : B. In Product system the machinery and equipment are fixed and in project system they are not fixed
57. Most important benefit to the consumer from efficient production system is:
A. He can save money
B. He will have product of his choice easily available
C. He gets increased use value in the product
D. He can get the product on credit.
Correct : C. He gets increased use value in the product
58. Two important functions that are to be done by Production department are:
A. Forecasting
B. Costing
C. Scheduling and loading
D. Inspecting.
Correct : C. Scheduling and loading
59. The act of releasing the production documents to the production department is known as:
A. Planning
B. Routing
C. Dispatching
D. Releasing
Correct : C. Dispatching
60. The activity of specifying when to start the job and when to end the job is known as:
A. Planning
B. Scheduling
C. Timing
D. Follow-up.
Correct : B. Scheduling
61. In an organisation the production planning and control department comes under:
A. Planning department
B. Manufacturing department
C. Personal department
D. R & D department.
Correct : B. Manufacturing department
62. In Job production system, we need:
A. More unskilled labours
B. Skilled labours
C. Semi-skilled labours
D. Old people
Correct : B. Skilled labours
63. In Continuous manufacturing system, we need:
A. General purpose machines and Skilled labours
B. Special machine tools and highly skilled labours
C. Semi automatic machines and unskilled labours
D. General purpose machines and unskilled labours.
Correct : B. Special machine tools and highly skilled labours
64. Most suitable layout for Job production is:
A. Line layout
B. Matrix layout
C. Process layout
D. Product layout.
Correct : C. Process layout
65. Most suitable layout for Continuous production is:
A. Line layout
B. Process Layout
C. Group technology
D. Matrix layout.
Correct : A. Line layout
66. One of the product examples for Line layout is:
A. Repair workshop
B. Welding shop
C. Engineering College
D. Cement.
Correct : D. Cement.
67. The act of going round the production shop to note down the progress of work and feedback the information is known as:
A. Follow up
B. Dispatching
C. Routing
D. Trip card
Correct : A. Follow up
68. Line of Best fit is another name given to:
A. Method of Least Squares
B. Moving average method
C. Semi average method
D. Trend line method
Correct : A. Method of Least Squares
69. One of the important basic objectives of Inventory management is:
A. To calculate EOQ for all materials in the organisation
B. To go in person to the market and purchase the materials
C. To employ the available capital efficiently so as to yield maximum results
D. Once materials are issued to the departments, personally check how they are used.
Correct : C. To employ the available capital efficiently so as to yield maximum results
70. The best way of improving the productivity of capital is:
A. Purchase automatic machines
B. Effective Labour control
C. To use good financial management
D. Productivity of capital is to be increased through effective materials management.
Correct : D. Productivity of capital is to be increased through effective materials management.
71. The cycle time, selected in balancing a line must be:
A. Must be greater than the smallest time element given in the problem
B. Must be less than the highest time element given in the problem
C. Must be slightly greater than the highest time element given in the problem
D. Left to the choice of the problem solver.
Correct : C. Must be slightly greater than the highest time element given in the problem
72. Production planning deals with:
A. What production facilities is required and how these facilities should be laid out in space available
B. What to produce and when to produce and where to sell
C. What should be the demand for the product in future?
D. What is the life of the product?
Correct : A. What production facilities is required and how these facilities should be laid out in space available
73. In Process Planning we plan:
A. Different machines required
B. Different operations required
C. We plan the flow of material in each department
D. We design the product.
Correct : C. We plan the flow of material in each department
74. In Operation Planning:
A. The planner plans each operation to be done at work centers and the sequence of operations
B. Decide the tools to be used to perform the operations
C. Decide the machine to be used to perform the operation,
D. Decide the materials to be used to produce the product.
Correct : A. The planner plans each operation to be done at work centers and the sequence of operations
75. Before thinking of routing, the production planner has to:
A. Decide the optimal allocation of available resources
B. To decide what type of labour to be used
C. To decide how much of material is required
D. To count how many orders he has on his hand.
Correct : A. Decide the optimal allocation of available resources
76. The quantities for which the planner has to prepare production plan are known as:
A. Optimal quantity of products
B. Material planning
C. Quantity planning
D. Planning quantity standards.
Correct : D. Planning quantity standards.
77. The document, which is used to show planning quantity standards and production plan, is known as:
A. Planning specifications
B. Route sheet
C. Bill of materials
D. Operation sheet
Correct : A. Planning specifications
78. In solving a problem on LOB, the number of workstations required is given by:
A. Cycle time/Total time
B. Cycle time/Element time
C. Total time/Element time
D. Total time/ Cycle time.
Correct : D. Total time/ Cycle time.
79. Final stage of production planning, where production activities are coordinated and projected on a time scale is known as:
A. Scheduling
B. Loading
C. Expediting
D. Routing
Correct : A. Scheduling
80. The study of relationship between the load on hand and capacity of the work centers is known as:
A. Scheduling
B. Loading
C. Routing
D. Controlling
Correct : B. Loading
81. One of the aims of loading is:
A. To finish the job as early as possible
B. To minimise the material utilization
C. To improve the quality of product
D. To keep operator idle time, material waiting time and ancillary machine time at
Correct : D. To keep operator idle time, material waiting time and ancillary machine time at
82. One of the principles of Scheduling is:
A. Principle of optimal product design
B. Principle of selection of best material
C. Principle of optimal operation sequence
D. Principle of optimal cost.
Correct : C. Principle of optimal operation sequence
83. One of the requirements of Aggregate Planning is:
A. Both output and sales should be expressed in a logical overall unit of measuring
B. Appropriate time period
C. List of all resources available
D. List of operations required.
Correct : A. Both output and sales should be expressed in a logical overall unit of measuring
84. In aggregate planning, one of the methods in modification of demand is:
A. Differential Pricing
B. Lay off of employees
C. Over time working
D. Sub contracting.
Correct : A. Differential Pricing
85. In aggregate planning one of the methods used to modification of supply is:
A. Advertising and sales promotion
B. Development of complimentary products
C. Backlogging
D. Hiring and lay off of employees depending on the situation.
Correct : D. Hiring and lay off of employees depending on the situation.
86. The first stage of Production control is:
A. Dispatching
B. Scheduling
C. Routing
D. Triggering of production operations and observing the progress and record the
Correct : D. Triggering of production operations and observing the progress and record the
87. One of the important production documents is:
A. Design sheet of the product
B. List of materials
C. Route card
D. Control chart
Correct : C. Route card
88. The way in which we can assess the efficiency of the production plant is by:
A. Efficient dispatching
B. By manufacturing a good product
C. By comparing the actual performance with targets specified in the specified programme
D. By efficient production planning.
Correct : C. By comparing the actual performance with targets specified in the specified programme
89. Production control concerned with:
A. Passive assessment of plant performance
B. Strict control on labours
C. Good materials management
D. Good product design
Correct : A. Passive assessment of plant performance
90. When work centers are used in optimal sequence to do the jobs, we can:
A. Minimise the set up time
B. Minimse operation time
C. Minimise the breakdown of machines
D. Minimise the utility of facility.
Correct : A. Minimise the set up time
91. One of the activities of expediting is:
A. To file the orders in sequence
B. To decide the sequence of operation
C. To record the actual production against the scheduled production
D. To examine the tools used in production
Correct : C. To record the actual production against the scheduled production
92. ‘Z’ chart is a chart used in:
A. Programme control
B. Job control
C. Cost control
D. Quality control
Correct : A. Programme control
93. Z-chart can be used to show:
A. Process used in production
B. Quality level of the product
C. Both the plan and the performance, and deviation from the plan
D. To show cost structure of the product.
Correct : C. Both the plan and the performance, and deviation from the plan
94. Computers are used in Production control in this area:
A. Follow-up activity
B. To control labour
C. To disseminate information
D. Loading, Scheduling and Assignment works.
Correct : D. Loading, Scheduling and Assignment works.
95. The following establishes time sequence of operations:
A. Routing
B. Sequencing
C. Scheduling
D. Dispatching
Correct : C. Scheduling
96. Arrangement of machines depending on sequence of operations happens in:
A. Process Layout
B. Product Layout
C. Hybrid Layout
D. Group Technology Layout.
Correct : B. Product Layout
97. Issuing necessary orders, and taking necessary steps to ensure that the time targets set in the schedules are effectively achieved is known as:
A. Routing
B. Dispatching
C. Scheduling
D. Inspection.
Correct : B. Dispatching
98. The card which is prepared by the dispatching department to book the labour involved in each operation is:
A. Labour card
B. Wage card
C. Credit card
D. Job card.
Correct : B. Wage card
99. Addition of value to raw materials through application of technology is:
A. Product
B. Production
C. Advancement
D. Transformation.
Correct : B. Production
100. The most powerful and popular method for solving linear programming problem is
A. Simplex method
B. Graphical method
C. Transportation method
D. Assignment method
Correct : A. Simplex method