Principles of Management | Set 6

1. Operations research approach is

Correct : A. Multi disciplinary

2. An optimization model

Correct : D. All of the above

3. OR provides solution only if the elements are

Correct : A. Quantified

4. The name management science is preferred by

Correct : A. Americans

5. Operations research is applied

Correct : D. All of the above

6. The application of OR techniques involves ………… approach

Correct : B. Team

7. OR techniques helps to find ………..solution

Correct : C. Optimal

8. Modern scientific management research originated during ……

Correct : A. World war II

9. ………. helps management to evaluate alternative course of action for selecting the best course of action

Correct : A. Operations research

10. ………. Theory is an important operations research technique to analyze the queuing behaviour.

Correct : A. Waiting line

11. ……….. is an important Operations research technique to be used for determining optimal allocation of limited resources to meet the given objectives.

Correct : D. Linear programming

12. ………… model involves all forms of diagrams

Correct : A. iconic

13. An organization chart is an example of

Correct : C. Analogue

14. …. Is known as symbolic model

Correct : B. Mathematical

15. A map indicates roads, highways, towns and the interrelationship is an ……model

Correct : C. analogue

16. ………..models in which the input and output variables follow a probability distribution.

Correct : D. Deterministic model

17. ………. Example of probabilistic model

Correct : A. Game theory

18. ………..is a method of analyzing the current movement of the same variable in an effort to predict the future movement of the same variable.

Correct : B. Markov analysis

19. Constraints in an LP model represent

Correct : D. all of the above

20. Linear programming is a

Correct : D. all of the above

21. A constraint in an LP model restricts

Correct : D. all of the above

22. The best use of linear programming technique is to find an optimal use of

Correct : D. all of the above

23. Which of the following as an assumption of an LP model

Correct : D. all of the above

24. Most of the constraints in the linear programming problem are expressed as ……….

Correct : B. Inequality

25. The graphical method of LP problem uses

Correct : D. All the above

26. A feasible solution to a linear programming problem

Correct : A. Must satisfy all problem constraints simultaneously

27. While plotting constraints on a graph paper, terminal points on both axes are connected by a straight line because

Correct : C. The constraints are linear equations or in equalities

28. Constraints in LP problem are called active if they

Correct : A. Represent optimal solution

29. The solution space of a LP problem is unbounded due to

Correct : C. Neither (a) nor (b)

30. While solving LP problem graphically, the area bounded by the constraints is called

Correct : A. Feasible region

31. Which of the following is not a category of linear programming problems?

Correct : D. All of the above are categories of linear programming problems.

32. A linear programming model does not contain which of the following components?

Correct : D. A spread sheet

33. Which of the following may not be in a linear programming formulation?

Correct : B. >.

34. While solving an LP problem infeasibility may be removed by

Correct : C. Removing a constraint

35. Straight lines shown in a linear programming graph indicates

Correct : B. Constraints

36. All negative constraints must be written as

Correct : C. Greater than or equal to

37. In linear programming problem if all constraints are less than or equal to, then the feasible region is

Correct : B. Below the lines

38. ……… is a series of related activities which result in some product or services.

Correct : A. Network

39. Any activity which does not consume either any resource or time is called ………..activity.

Correct : C. Dummy

40. An activity which must be completed before one or more other activities start is known as ……….activity.

Correct : A. Predecessor

41. Activities that cannot be started until one or more of the other activities are completed, but immediately succeed them are called ……activities

Correct : B. Successor

42. An event which represents the beginning of more than one activity is known as ………..event.

Correct : C. Burst

43. If two constraints do not intersect in the positive quadrant of the graph, then

Correct : D. None of the above

44. Constraint in LP problem are called active if they

Correct : A. Represent optimal solution

45. Alternative solutions exists of an LP model when

Correct : B. Objective function equation is parallel to one of the constraints

46. While solving an LP problem, infeasibility may be removed by

Correct : C. Removing a constraint

47. ………is that sequence of activities which determines the total project time.

Correct : B. Critical path

48. Activities lying on the critical path are called………….

Correct : C. Critical activities

49. It ………. at which an activity can start.

Correct : A. EST

50. ………… is the earliest starting time plus activity time.

Correct : B. EFT

51. ………. is the latest time by which an activity can be started without delaying the completion of the project.

Correct : C. LST

52. ……….is the latest time by which an activity can be finished without delaying the completion of the project.

Correct : D. LFT

53. ……………is the duration by which an activity can be delayed without delaying the project

Correct : B. Total float

54. ……… is the time by which the completion of an activity can be delayed beyond its earliest finish time without affecting the earliest start time of a succeeding activity

Correct : C. Free float

55. ……….is activity oriented.

Correct : A. CPM

56. ………. is event oriented.

Correct : B. PERT

57. PERT emphasis on ………..

Correct : A. Time

58. Full form of PERT is

Correct : A. Performance evaluation review technique

59. …….. is a scheme or design of something intended or device.

Correct : C. Network

60. An activity which must be completed before one or more other activities start is known as …………activity.

Correct : B. Predecessor

61. The event is commonly represented by …… in network diagram

Correct : A. Nodes

62. …….is the disconnection of an activity before the completion of activities in a project network diagram.

Correct : C. Dummy

63. …………. is an activity oriented diagram.

Correct : A. CPM

64. ………… is the duration by which an activity can be delayed without delaying the project.

Correct : A. Total float

65. ………is the shortest possible time in which an activity can be delayed without delaying the project.

Correct : B. Optimistic time estimate

66. Which of the following is not a part of decision tree problem specification?

Correct : C. EVPI

67. If a decision theory problem has 3 decision alternatives and 4 states of nature, the number of payoffs in that problem will be

Correct : C. 12

68. In a decision theory problem under complete uncertainty, which one of the following approaches will not be possible?

Correct : A. Expected monetary value

69. For decision making under uncertainty, identify the decision rule that is appropriate for the optimist.

Correct : B. Maximax

70. What decision-making condition must exist for the decision tree to be a valuable tool?

Correct : C. Risk

71. Which of the following is (are) types of decision-making environments?

Correct : B. Decision making under certainty

72. A good decision always implies that

Correct : D. Have followed a logical process.

73. All of the following are steps in the decision-making process EXCEPT

Correct : D. Compute the posterior probabilities.

74. The equally likely decision criteria is also known as

Correct : B. Laplace

75. Opportunity loss refers to

Correct : C. The difference between actual pay off and the optimal pay off

76. The criteria of expected monetary value is used for making decisions under

Correct : D. all of the above

77. The maximax criteria is……..

Correct : C. Pessimistic

78. Which of the following might be viewed as an optimistic decision criterion?

Correct : C. Maximax

79. The minimum EOL will always result in the same decision as

Correct : C. Maximum EMV

80. Decision theory is concerned with

Correct : D. All of the above

81. Which of the following criterion is not used for decision making under uncertainty?

Correct : D. Minimize expected loss

82. The minimum expected opportunity loss is

Correct : D. Both (a) and (b)

83. The expected value of perfect information is equal to

Correct : A. EPPI – Minimum EMV

84. The value of the coefficient of optimism is needed while using the criterion of

Correct : C. Realism

85. While using Hurwicz criterion, the coefficient of realism

Correct : A. Represents the degree of optimism

86. The decision making criteria that should be used to achieve maximum long term pay off is

Correct : B. EMV

87. Game theory models are classified by the

Correct : D. All of the above

88. The objective of network analysis is to

Correct : A. Minimize total project duration

89. The initial solution of a transportation problem can be obtained by applying any known method. But the only condition is

Correct : B. The rim conditions are satisfied

90. When total supply is equal to total demand in a transportation problem , the problem is said to be

Correct : A. Balanced