1. The rate of payment is made for 100 cu m (per % cu m) in case of
Correct : D. all the above
2. The rate of an item of work depends on
Correct : D. all the above
3. The main factor to be considered while preparing a detailed estimate, is
Correct : D. all the above
4. Brick walls are measured in sq. m if the thickness of the wall is
Correct : A. 10 cm
5. The plinth area of a building not includes
Correct : D. area of cantilevered porch
6. If the formation level of a highway has a uniform gradient for a particular length, and the ground is
also having a longitudinal slope, the earthwork may be calculated by
Correct : D. all the above
7. A cement concrete road is 1000 m long, 8 m wide and 15 cm thick over the sub-base of 10 cm thick
gravel. The box cutting in road crust is
Correct : C. 1500 m3
8. While estimating the qualities for the construction of a building, the correct metric unit is
Correct : D. litre for capacity
9. The brick work is not measured in cu m in case of
Correct : D. half brick wall
10. The assumption on which the trapezoidal formula for volumes is based, is
Correct : D. all the above
11. In the mid-section formula
Correct : D. all of the above
12. Pick up the correct statement from the following:
Correct : D. all the above
13. The cross-sections for a highway is taken at
Correct : D. all the above
14. Referring of given figure, pick up the correct statement from the following:
Correct : D. all the above
15. According to Indian Standards Institute, the actual size of modular bricks is
Correct : C. 19 cm × 9 cm × 9 cm
16. The following item of earth work is not measured separately.
Correct : D. all the above
17. The measurement is made in square metre in case of
Correct : D. none of these
18. Cost of fittings and their fixing is specified for the following sanitary fittings
Correct : D. all the above
19. The excavation exceeding 1.5 m in width and 10 sq.m in plan area with a depth not exceeding 30
cm, is termed as
Correct : D. surface excavation
20. For the construction of buildings, the subheads of the estimate are
Correct : D. all the above
21. Pick up the correct statement from the following:
Correct : D. all the above
22. The cross-section of a road partly in banking and partly in cutting is shown in the given figure. The
area of the shaded portion is
Correct : A. b - rd)²/(r - s)
23. Pick up the correct statement from the following:
Correct : D. all the above
24. Pick up the incorrect statement from the following:
Correct : D. none of these
25. The value of 'B' of Indian type W.C. shown in the given figure is:
Correct : A. 45 cm
26. Pick up the excavation where measurements are made in square metres for payment.
Correct : D. both (b) and (c)
27. As per Indian Standard Specifications, the peak discharge for domestic purposes per capita per
minute, is taken
Correct : D. all the above
28. In long and short wall method of estimation, the length of long wall is the centre to centre
distance between the walls and
Correct : B. half breadth of wall on each side
29. The expected out turn of cement concrete 1 : 2 : 4 per mason per day is
Correct : D. 5.0 m3
30. The value of 'C' of Indian type W.C. shown in the given figure is:
Correct : C. 500 mm
31. The area is measured correct to the nearest
Correct : A. 0.01 sqm
32. The measurement is not made in square metres in case of
Correct : D. r.c. chhajja
33. The value of 'A' of Indian type W.C. shown in the given figure is:
Correct : B. 30 cm
34. The trap which is provided to disconnect the house drain from the street sewer is called
Correct : D. all the above
35. Due to change in price level, a revised estimate is prepared if the sanctioned estimate exceeds
Correct : D. 5.0 %
36. The cost of the earthwork in excavation for the surface drain of cross-section shown in the given
figure for a total length of 5 metres @ Rs. 450% cum, is
Correct : C. rs. 450
37. The expected out turn of 2.5 cm cement concrete floor per mansion per day
Correct : C. 7.5 sqm
38. Pick up the correct statement from the following:
Correct : D. all the above
39. While preparing a detailed estimate
Correct : D. all the above
40. The item of the brick structure measured in sq.m, is
Correct : B. broken glass coping
41. The most reliable estimate is
Correct : A. detailed estimate
42. According to ISI method of measurement, the order of the sequence is
Correct : A. length, breadth, height
43. Anti-siphonage pipe is connected to
Correct : C. top of p trap w.c.
44. Pick up the correct statement from the following:
Correct : B. the gully trap collects waste water from the kitchen, sink, wash basins, etc.
45. Pick up the correct statement from the following:
Correct : D. all the above
46. Pick up the correct statement from the following:
Correct : D. all the above
47. Pick up the correct statement in case of water supply.
Correct : D. all the above
48. The concrete work for the following part of the building of specified thickness is measured in
square metres
Correct : D. all the above
49. The expected out turn of 12 mm plastering with cement mortar is
Correct : D. 8.0 sq m
50. The total length of a cranked bar through a distance (d) at 45° in case of a beam of effective
length L, is
Correct : B. l + (2 × 0.42 d)
51. The measurement is made for stone work in square metre in case of
Correct : D. (a) and (d) of the above
52. Carpet area does not include the area of
Correct : D. all the above
53. The cross-sectional area of the embankment of a canal fully in embankment in the given figure is
Correct : C. ( + ) + 2sh²
54. The correct Prismoidal formula for volume is
Correct : B. d/3 [first area + last area + 4 even area + 2 odd areas]
55. In case of laying gullies, siphons, intercepting traps, the cost includes
Correct : D. all of these
56. The inspection pit or chamber is a manhole provided in a base drainage system
Correct : D. all the above
57. Pick up the incorrect statement from the following:
Correct : C. cubic contents are measured to the nearest 0.1 cum
58. The 'centre line method' is specially adopted for estimating
Correct : D. all the above
59. Pick up the incorrect statement from the following:
Correct : D. none of these
60. The unit of measurement is per quintal for the following:
Correct : D. m.s. reinforcement of r.c.c. works
61. The diameter of a domestic sewer pipe laid at gradient 1 in 100 is recommended
Correct : B. 150 mm
62. The order of booking dimensions is
Correct : A. length, breadth, height
63. Pick up the incorrect statement regarding a master trap from the following:
Correct : D. the water seal is less than that of ordinary traps
64. S: 1 and
length is
Correct : C. l.d 1 + s2)
65. The detention period in a septic tank is assumed
Correct : C. 30 minutes
66. Pick up the item of work not included in the plinth area estimate
Correct : D. courtyard area
67. The minimum width of a septic tank is taken
Correct : B. 75 cm
68. Pick up the item whose weight is added to the weight of respective item, is
Correct : D. all the above
69. The expected out turn for earth work in excavation in ordinary soil per workman per day is
Correct : C. 3.00 cum
70. The expected out turn of brick work in cement mortar in foundation and plinth per mason per day,
is
Correct : B. 1.25 m3
71. The brick work is measured in sq metre, in case of
Correct : D. all the above
72. The height of the sink of wash basin above floor level is kept
Correct : C. 75 cm to 80 cm
73. For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement
required, is
Correct : C. 0.274 m3
74. The item of steel work which is measured in sq.m, is
Correct : D. all the above
75. The damp proof course (D.P.C.) is measured in
Correct : B. sq. m
76. The volume is measured correct to the nearest
Correct : A. 0.01 cum
77. For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is
Correct : B. 0.94 m3
78. Size, capacity and materials need be specified for
Correct : D. all the above
79. The expected out turn of half brick partition wall per mason per day is
Correct : B. 2.0 m3
80. The floor area includes the area of the balcony up to
Correct : C. 50 %
81. The slope of the outlet of 'P trap' below the horizontal is kept
Correct : D. 14°
82. The weight of an item is measured correct to nearest
Correct : D. 1.00 kg
83. Berms are provided in canals if these are
Correct : B. partly in excavation and partly in embankment