1. The notice inviting tender should published in minimum........ daily news paper
A. 3
B. 2
C. 4
D. 5
Correct : B. 2
2. Who will sign the contract deed on behalf of government
A. Chief engineer
B. Superintendent engineer
C. Executive engineer
D. Head clerk
Correct : C. Executive engineer
3. Who will draft contract agreement?
A. Chief engineer
B. Divisional head clerk
C. Executive engineer
D. None of the above
Correct : B. Divisional head clerk
4. Which are the criteria to be checked for pre- qualification of contractor
A. Financial strength
B. Past five year experience
C. Technical personnel engaged
D. All of the above
Correct : D. All of the above
5. How many envelops are required to submitted Tender form
A. 3
B. 1
C. 4
D. 2
Correct : C. 4
6. Total no of grades for registration of contractor with governments are
A. 3
B. 5
C. 7
D. 4
Correct : C. 7
7. Contract is terminated in case of
A. Slow progress and time limit exceeds
B. Work is not being executed as per specifications and instruction of EIC
C. Contractor tries to admit sub-contractor
D. All of the above
Correct : D. All of the above
8. Form no .........is used for material at site account
A. 35
B. 28
C. 16
D. 9
Correct : A. 35
9. Mobilization advance
A. Shall be 2 to 5 % of project cost.
B. Shall be 3 to 7 % of project cost.
C. Shall be 10 to 15 % of project cost.
D. Shall be 12 to 18 % of project cost.
Correct : A. Shall be 2 to 5 % of project cost.
10. Stock account is cleared yearly while tools and plants account is cleared half yearly
A. TRUE
B. FALSE
C. none
D. all
Correct : B. FALSE
11. PERT analysis is based upon
A. Optimistic time
B. Pessimistic time
C. Most likely time
D. All of the above
Correct : D. All of the above
12. The time activity consumes in most adverse conditions is
A. Optimistic time
B. Pessimistic time
C. Most likely time
D. All of the above
Correct : B. Pessimistic time
13. The time activity consumes in normal conditions is
A. Optimistic time
B. Pessimistic time
C. Most likely time
D. All of the above
Correct : C. Most likely time
14. The difference between the total float and free float is called
A. Duration
B. Interfering float
C. Critical activity
D. None of the above
Correct : B. Interfering float
15. The critical path is
A. The longest path of the network
B. The shortest path of the network
C. The average duration path of the network
D. None of the above
Correct : A. The longest path of the network
16. The float of critical activity is always
A. Maximum
B. Minimum
C. Zero
D. None of the above
Correct : C. Zero
17. A dummy activity in a network
A. Is represented by dotted line
B. Is an artificial activity
C. Does not consume time and resources
D. All of the above
Correct : D. All of the above
18. Activity starts from
A. Head event
B. Tail event
C. Dual role event
D. None of the above
Correct : B. Tail event
19. Which of the following is an activity
A. Excavation
B. Curing
C. Laying concrete
D. All of the above
Correct : D. All of the above
20. Earliest start time of activity equals to
A. TE of tail event of an activity
B. TE of head event of an activity
C. Average time of TE of tail event and head event
D. None of the above
Correct : A. TE of tail event of an activity
21. ................is provided to safeguard scaffolding against overturning.
A. Standards
B. Inclined rackers
C. Put-logs
D. Rails
Correct : B. Inclined rackers
22. Ladder leading to landing should be extended at least ....... meter above the landing
A. 1.2
B. 1.5
C. 1
D. 1.8
Correct : C. 1
23. While using ladder one should not lean sideways more than......... cms.
A. 40
B. 60
C. 30
D. 45
Correct : C. 30
24. Wooden ladders should be inspected at least........... a month.
A. Once
B. Twice
C. Three times
D. Four times
Correct : A. Once
25. In sheds for ceiling works, ......................... scaffolding is economical.
A. Suspended
B. Needle
C. Ordinary
D. None of the above
Correct : A. Suspended
26. The construction industry has accounted for about ............% of all deaths due to accident at place of work
A. 5
B. 20
C. 25
D. 30
Correct : B. 20
27. For repair works at high level of multistoreyed buildings needle scaffolding is preferred
A. As it is more stable
B. As it looks better
C. As it will not obstruct traffic at ground level.
D. None of the above
Correct : C. As it will not obstruct traffic at ground level.
28. PPE stands for
A. Personal protective equipment
B. Preferred protective equipment
C. Prohibited protective equipment
D. None of the above
Correct : A. Personal protective equipment
29. For work at height one should use
A. Safety belt
B. Full body harness
C. none
D. all
Correct : B. Full body harness
30. A good safety record can produce higher morale, productivity and stronger employee loyalty.
A. Right
B. Wrong
C. none
D. all
Correct : A. Right
31. Who plays a crucial role in convincing the operating staff to adopt the change?
A. HRD manager
B. Junior engineer
C. Public relation officer
D. Supervisor
Correct : D. Supervisor
32. Supervisor is at the lowest level of management
A. Right
B. Wrong
C. none
D. all
Correct : A. Right
33. ............. has 3 roles ;Trainer,Motivator and Facilitator
A. HRD manager
B. Junior engineer
C. Public relation officer
D. Supervisor
Correct : D. Supervisor
34. HRD is mainly concerned with
A. Optimum stress
B. Optimum cost
C. Optimum duration
D. None of the above
Correct : A. Optimum stress
35. Which one of the following is not a system of HRD
A. Optimization of resources system
B. Appraisal system
C. Carrier system
D. Training System
Correct : A. Optimization of resources system
36. Human resource is a
A. Perishable resource
B. Dynamic resource
C. Both A and B
D. None of the above
Correct : C. Both A and B
37. Human resource development (HRD) is a
A. Process
B. Previlege
C. Business cycle
D. None of the above
Correct : A. Process
38. HRD is a process which progresses by
A. Proper management of resource
B. customer satisfaction
C. Time resource optimization
D. Performance appraisal,Counseling and training
Correct : D. Performance appraisal,Counseling and training
39. MIS stands for
A. Management Innovation System
B. Management Information System
C. Management Interaction style
D. None of the above
Correct : B. Management Information System
40. HRD stands for
A. Human resource development
B. Human resource design
C. Higher resource development
D. None of the above
Correct : A. Human resource development
41. In one stack not more than.......... cement bags should be stored one above other.
A. 8
B. 10
C. 15
D. 12
Correct : D. 12
42. The space between the walls and cement bags all-round should be at least......... cms.
A. 30
B. 50
C. 60
D. 40
Correct : A. 30
43. EOQ stands for
A. Equal order quantity
B. Economic order quantity
C. Extra order quantity
D. None of the above
Correct : B. Economic order quantity
44. Timber and plywood should be stacked separately.
A. Agree
B. Disagree
C. none
D. all
Correct : A. Agree
45. In any construction project the material cost constitute about..... % of the total project cost.
A. 60
B. 25
C. 35
D. 45
Correct : A. 60
46. While placing of concrete, it should not be dropped from more than .......m height.
A. 2
B. 1
C. 3
D. 4
Correct : B. 1
47. The coarse aggregates of different sizes like 5 to 10 mm, 10 to 20 mm, 20 to 40 mm etc. should be stored in different piles.
A. Agree
B. Disagree
C. none
D. all
Correct : A. Agree
48. Which of the following is not a principle of preparing job layout
A. Location of auditorium
B. Administrative block
C. Warehouses/godown
D. Entry and Exit
Correct : A. Location of auditorium
49. Which of the following is not a purpose of making job layout
A. To develop human resources in organization
B. To save time of delivery of material
C. To safeguard material from wastage and theft
D. To keep lead minimum
Correct : A. To develop human resources in organization