Quiznetik

Construction Project Management | Set 2

1. The notice inviting tender should published in minimum........ daily news paper

Correct : B. 2

2. Who will sign the contract deed on behalf of government

Correct : C. Executive engineer

3. Who will draft contract agreement?

Correct : B. Divisional head clerk

4. Which are the criteria to be checked for pre- qualification of contractor

Correct : D. All of the above

5. How many envelops are required to submitted Tender form

Correct : C. 4

6. Total no of grades for registration of contractor with governments are

Correct : C. 7

7. Contract is terminated in case of

Correct : D. All of the above

8. Form no .........is used for material at site account

Correct : A. 35

9. Mobilization advance

Correct : A. Shall be 2 to 5 % of project cost.

10. Stock account is cleared yearly while tools and plants account is cleared half yearly

Correct : B. FALSE

11. PERT analysis is based upon

Correct : D. All of the above

12. The time activity consumes in most adverse conditions is

Correct : B. Pessimistic time

13. The time activity consumes in normal conditions is

Correct : C. Most likely time

14. The difference between the total float and free float is called

Correct : B. Interfering float

15. The critical path is

Correct : A. The longest path of the network

16. The float of critical activity is always

Correct : C. Zero

17. A dummy activity in a network

Correct : D. All of the above

18. Activity starts from

Correct : B. Tail event

19. Which of the following is an activity

Correct : D. All of the above

20. Earliest start time of activity equals to

Correct : A. TE of tail event of an activity

21. ................is provided to safeguard scaffolding against overturning.

Correct : B. Inclined rackers

22. Ladder leading to landing should be extended at least ....... meter above the landing

Correct : C. 1

23. While using ladder one should not lean sideways more than......... cms.

Correct : C. 30

24. Wooden ladders should be inspected at least........... a month.

Correct : A. Once

25. In sheds for ceiling works, ......................... scaffolding is economical.

Correct : A. Suspended

26. The construction industry has accounted for about ............% of all deaths due to accident at place of work

Correct : B. 20

27. For repair works at high level of multistoreyed buildings needle scaffolding is preferred

Correct : C. As it will not obstruct traffic at ground level.

28. PPE stands for

Correct : A. Personal protective equipment

29. For work at height one should use

Correct : B. Full body harness

30. A good safety record can produce higher morale, productivity and stronger employee loyalty.

Correct : A. Right

31. Who plays a crucial role in convincing the operating staff to adopt the change?

Correct : D. Supervisor

32. Supervisor is at the lowest level of management

Correct : A. Right

33. ............. has 3 roles ;Trainer,Motivator and Facilitator

Correct : D. Supervisor

34. HRD is mainly concerned with

Correct : A. Optimum stress

35. Which one of the following is not a system of HRD

Correct : A. Optimization of resources system

36. Human resource is a

Correct : C. Both A and B

37. Human resource development (HRD) is a

Correct : A. Process

38. HRD is a process which progresses by

Correct : D. Performance appraisal,Counseling and training

39. MIS stands for

Correct : B. Management Information System

40. HRD stands for

Correct : A. Human resource development

41. In one stack not more than.......... cement bags should be stored one above other.

Correct : D. 12

42. The space between the walls and cement bags all-round should be at least......... cms.

Correct : A. 30

43. EOQ stands for

Correct : B. Economic order quantity

44. Timber and plywood should be stacked separately.

Correct : A. Agree

45. In any construction project the material cost constitute about..... % of the total project cost.

Correct : A. 60

46. While placing of concrete, it should not be dropped from more than .......m height.

Correct : B. 1

47. The coarse aggregates of different sizes like 5 to 10 mm, 10 to 20 mm, 20 to 40 mm etc. should be stored in different piles.

Correct : A. Agree

48. Which of the following is not a principle of preparing job layout

Correct : A. Location of auditorium

49. Which of the following is not a purpose of making job layout

Correct : A. To develop human resources in organization