Quiznetik

Construction Management | Set 2

1. Completion of an activity on CPM network diagram, is generally known

Correct : D. All the above

2. Assertion A: For a given depth of cut, the output of a power shovel can be increased by decreasing the angle of swing. Reason R: If the angle of swing is decreased, the cycle time will be decreased. Select the correct answer.

Correct : A. Both A and R is true and R is the correct explanation of A

3. The salient feature of functional organisation is

Correct : D. All the above

4. A tractor shovel has a purchase price of Rs. 4.7 lacs and could save the organization an amount of rupees one lac per year on operating costs. The salvage value after the amortization period is 10% of the purchase price. The capital recovery period will be

Correct : B. 4.23 years

5. The first method invented for planning projects, was

Correct : A. Bar chart method

6. Which one of the following is not an excavating and moving type of equipment?

Correct : D. Dump truck

7. The main disadvantage of line organisation, is

Correct : D. All the above

8. Batching refers to

Correct : C. Controlling the quantity of each material into each batch

9. While scheduling a project by C.P.M.

Correct : D. All the above

10. Slack time refers to

Correct : B. An event

11. Final technical authority of a project lies with

Correct : D. Chief Engineer

12. Whenever an activity has zero total float, then

Correct : C. Free float and independent float both must be zero

13. Mile Stone charts were invented in the year of

Correct : D. 1940

14. Which of the following is not a PERT event?

Correct : D. Class is being attended

15. A construction schedule is prepared after collecting

Correct : D. All the above

16. A tractor whose weight is 20 tonnes has a drawbar pull of 2500 kg, when operated on a level road having a rolling resistance of 30 kg per tonne. If this tractor is operated on a level road having a rolling resistance of 40 kg per tonne, then the drawbar pull of the tractor will

Correct : A. Reduce by 200 kg

17. Pick up the correct statement from the following:

Correct : D. All the above

18. In India, are prefabricated components costlier than those of traditional cast-in-situ items that the prefabricated components replace?

Correct : C. No, because of repetitive manufacture of a number of elements

19. Frequency distribution curves

Correct : D. All the above

20. The difference between the time avail-to do a job and the time required to do the job, is known as

Correct : B. Float

21. The grade resistance factor for an earth moving machine can be obtained by multiplying grade percentage by a factor approximately equal to

Correct : C. 9 kg/tonne

22. A dummy activity

Correct : D. All the above

23. The reduction in project time normally results in

Correct : B. Increasing the direct cost and decreasing the indirect cost

24. Frederick W. Taylor introduced a system of working known as

Correct : C. Functional organisation

25. The area under the Beta distribution curve is divided into two equal parts by

Correct : D. Expected time

26. CPM is

Correct : D. All the above

27. A four wheel truck or whose operating weight is 12000 kg is pulled along a road having a rising slope of 2% at a uniform speed. Assume grade resistance factor = 10 kg/tonne. The tension in the tow cable is 720 kg. The rolling resistance of the road will be

Correct : C. 40 kg/tonne

28. The Overall in-charge of an organisation at the site responsible for the execution of the works, is

Correct : B. Engineer

29. Consider the following features/factors: 1. Projects are of the non-repetitive type 2. Time required need not be known 3. Time required is known precisely 4. Events have been established for planning 5. Emphasis is given to activities ofproject PERT is preferred for planning becauseof

Correct : A. 1, 2 and 4

30. The first stage of a construction, is

Correct : C. Initiation of proposal

31. Crash project duration is obtained by summing the

Correct : D. Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities.

32. Pick up the correct statement from the following:

Correct : D. All the above

33. Sinking fund is

Correct : A. The fund for rebuilding a structure when its economic life is over

34. If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is

Correct : C. (a + 4m + b)/6

35. Consider the following statements for a power shovel: (i) Output can be increased by reducing the angle of swing for a given depth ofcut. (ii) For a given angle of swing, output will be maximum at optimum depth of cut. (iii) Output can be increased by keeping the depth of cut less than optimumdepth, (iv) Output can be increased by increasing the size of shovel. Of these statements

Correct : B. (i), (ii) and (iv) are correct

36. If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be

Correct : D. to + 4tm+ tp/6

37. The most suitable type of equipment for compaction of cohesive soils is

Correct : C. Sheep foot rollers

38. If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be

Correct : D. All the above

39. Rolling resistance of a wheel depends upon (i) Vehicle load (ii) Grade (iii) Ground conditions Of these statements

Correct : C. (i) and (iii) are correct

40. A Milestone chart

Correct : D. None of these

41. Earliest finish of an activity is always

Correct : C. Less than or equal to earliest event time of the following node

42. Critical path lies along the activities having total float

Correct : C. Zero

43. If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be

Correct : C. More than 50 %

44. The critical activity has

Correct : C. Zero float

45. For excavating utility trenches with precise control of depth, the excavation equipment used is

Correct : A. Hoe

46. PERT analysis is based on

Correct : D. All the above

47. The most popular type of organisation used for Civil Engineering Constructions, is

Correct : A. Line organisation

48. The probability of completion of any activity within its expected time is

Correct : A. 50 %

49. The performance of a specific task in CPM, is known

Correct : C. Activity

50. Pre-tender stage requires

Correct : D. All the above

51. An event is indicated on the network by a number enclosed in

Correct : D. All the above

52. Select the incorrect statement.

Correct : D. Critical activity is the one for which free float is zero.

53. If t is the duration of an activity, t1 is the latest finish possible moment of its preceding activity and t2 is the earliest start possible moment, the independent float of the activity is

Correct : A. (t1 - t2) - t

54. Free float for any activity is defined as the difference between

Correct : A. Its earliest finish time and earliest start time for its successor activity

55. In CPM analysis,

Correct : D. All the above

56. The estimated time required to perform an activity, is known as

Correct : C. Duration

57. Critical Path Net Work helps an engineer

Correct : D. All the above

58. B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he

Correct : A. Should invest in neither of the two projects

59. Henry Gantt developed Bar charts for planning and scheduling of projects in

Correct : B. 1900

60. If TL is the latest allowable event occurrence time, total activity slack(s), is equal to

Correct : D. All the above

61. Modular co-ordination of construction means proper

Correct : D. All the above

62. Pick up the correct statement from the following:

Correct : D. All the above

63. The final selection of a construction site, is done by

Correct : D. All the above

64. The main advantage of line organisation is:

Correct : D. All the above