Quiznetik

Project Management | Set 4

1. Optimal quality is reached at what point?

Correct : C. When revenue from improvement equals the incremental costs to achieve the quality

2. A communication management plan identifies the relevant information that should be communicated to:

Correct : B. the project stakeholders.

3. Project risk management is best described as:

Correct : D. minimising threats and maximising opportunities.

4. Which one of the following best describes a project issue?

Correct : A. A major problem that requires formal escalation.

5. The phases of a project life cycle are:

Correct : B. concept, definition, development, handover and closure.

6. Who are project team members primarily accountable to?

Correct : D. The project manager.

7. Who has ultimate responsibility for project risk?

Correct : C. Project sponsor.

8. Who owns the Project Management Plan (PMP)?

Correct : C. The project manager.

9. A project is typically defined in terms of scope, time, cost and which other parameter?

Correct : B. Quality.

10. Which of these is not one of the constraints of a project?

Correct : C. Team

11. Which of the following is NOT a project management cause of failed projects?

Correct : C. inadequate systems analysis and design tools

12. Which of the following is not considered as a risk in project management?

Correct : C. Testing

13. The process each manager follows during the life of a project is known as

Correct : C. Project Management Life Cycle

14. Quality planning is the process of developing a quality plan for

Correct : B. project

15. Which of the following is incorrect activity for the configuration management of a software system?

Correct : A. Internship management

16. Identify the sub-process of process improvement

Correct : B. Process analysis

17. Choose an internal software quality from given below:

Correct : C. reusability

18. A _________ is developed using historical cost information that relates some software metric to the project cost.

Correct : A. Algorithmic cost modelling

19. Which technique is applicable when other projects in the same analogy application domain have been completed?

Correct : C. Estimation by analogy

20. Which of the following states that work expands to fill the time available.

Correct : A. CASE tools

21. Which model is used during early stages of the system design after the requirements have been established?

Correct : A. An application-composition model

22. The team is responsible for exchange of information and process guidence either to or from project practitioners.

Correct : A. Software engineering process authority.

23. _________is the critical factor in understanding how to plan and execute a software development project.

Correct : D. Domain experience

24. ________focuses on developing change -tolerance software.

Correct : A. Rapid application development

25. successful projects recognize the continuous improvment towards the best value rather than adhering to__________.

Correct : A. Ambiguous statements

26. _______milestones occure at the end of the elaboration phase.

Correct : A. Life-style architecture