Quiznetik

Project Management | Set 3

1. Costs that are not directly related to the products or services of the project, but are indirectly related to performing the project.

Correct : D. Indirect Costs

2. Relationship based on unrelated level of activity and past data of cost is measured with help of

Correct : A. cost estimation

3. In estimation of cost functions, variations in a single activity level represents the

Correct : A. related total costs

4. The latest finish time for an activity:

Correct : A. Equals the min. of LFT − t for all immediate successors

5. Which of the following statements is true?

Correct : B. PERT is considered as a probabilistic techniques and CPM is considered as a deterministic approach.

6. In corporate costs, cost incurred to finance construction of new equipment are classified as

Correct : A. treasury costs

7. An uncertain event or condition that, if it occurs, has a positive or negative effect on a project objectives is termed.

Correct : C. Risk

8. The cost impact of a risk event occurring as a project proceeds through its life cycle tends to

Correct : A. Slowly rise

9. Evaluation process of proposed projects or groups of projects is known as:

Correct : C. Project selection

10. Nature of interrelationships between components in a system defines the

Correct : B. Structure of system

11. Listing goals of each existing and proposed project is first step in

Correct : D. Identification of project categories

12. For any project word objective is held to be synonymous with

Correct : A. Fact

13. Which of these is not one of the constraints of a project?

Correct : C. Team

14. Which of the following is not correct about initial phase of a project?

Correct : A. The cost associated at the beginning of the project is highest.

15. Which is the first stage in the project management model?

Correct : A. Understanding the project environment

16. A clear hierarchy of objectives in the project definition would NOT normally contain:

Correct : D. Control mechanisms

17. Which of the following is a factor that influences project selection?

Correct : D. All of the above

18. The primary deliverable from the project identification and selection phase is a:

Correct : A. schedule of specific IS development projects.

19. When classifying and ranking projects, which of the following refers to the amount and type of resources the project requires and their availability?

Correct : C. Resource availability

20. When classifying and ranking projects, which of the following refers to the extent to which the project is viewed as helping the organization achieve its strategic objectives and longterm goals?

Correct : C. Strategic alignment

21. During feasibility analysis it is necessary to examine several alternative solutions because (i) a comparison of alternatives will lead to a cost-effective solution (ii) a pre-conceived single solution may turn out to be unimplementable (iii) it is always good to examine alternatives (iv) management normally looks at alternatives

Correct : C. i and ii

22. Goals are identified by

Correct : B. pinpointing unsatisfactory performance

23. By technical feasibility of a solution we mean that

Correct : A. technology is available to implement it

24. By operational feasibility we mean

Correct : C. the system can be adapted by an organization without major disruptions

25. By economic feasibility of a system we mean that

Correct : D. finances are available to implement the system and it will be cost – effective

26. The following are the most important points of a detailed system proposal (i) who will supply and install the required equipment (ii) cost-benefit analysis (iii) comparison of alternative solutions (iv) implementation plan

Correct : C. ii, iii and iv

27. At the end of the feasibility study the systems analyst

Correct : B. gives a summary feasibility report to the management

28. The process of determining whether an entrepreneur's idea is a viable foundation for creating a successful business is known as a:

Correct : A. feasibility analysis

29. A cost-benefit analysis is performed to assess

Correct : A. economic feasibility

30. The primary objective of cost-benefit analysis is

Correct : C. to determine if it is economically worthwhile to invest in developing the information system

31. The following assumptions are made in case of break even analysis, except

Correct : B. All variable costs are fixed

32. At breakeven point there is

Correct : C. No profit or loss

33. Which of the following should be taken into account when planning a project?

Correct : D. All of the above

34. Improvement efforts are determined by:

Correct : D. All of the above

35. Performance measurement is:

Correct : B. The process of quantifying action.

36. Performance relating to the five operations’ objectives can be plotted on which type of diagram?

Correct : C. Polar

37. Which kind of standards are those that are set arbitrarily to reflect some level of performance that is regarded as appropriate or reasonable?

Correct : B. Target performance standards

38. For a police department, using competitor performance standards, a competitor might be:

Correct : D. All of the above

39. What approach is used to compare organisation operations with those of other companies?

Correct : C. Benchmarking

40. The origins of benchmarking as it is used today go back to which company?

Correct : C. Xerox

41. A comparison between operations or parts of operations that are within the same total organisation is called:

Correct : A. Internal benchmarking

42. Benchmarking against external organisations that do not compete directly in the same markets is called:

Correct : A. Non-competitive benchmarking

43. Which of the following is regarded as a fundamental flaw in the whole concept of benchmarking?

Correct : A. It limits improvements to currently accepted methods of operating.

44. What matrix positions each factor according to its performance and its importance?

Correct : C. Importance performance matrix

45. What do the letter ‘D’ and ‘I’ stand for in Deming’s cycle of improvement?

Correct : D. Define and improve

46. Ishikawa Diagrams are another name for what technique of improvement?

Correct : A. Cause-effect diagrams

47. The principles of the business process re-engineering (BPR) approach do NOT include:

Correct : B. Scrapping any process line over two years old and starting again from scratch.

48. Qualifying competitive factors are those which:

Correct : D. May not win extra business if the operation improves its performance but can certainly lose business if performance falls below a particular point.

49. Which of the following is not a tool and technique used in the process of Plan Risk Responses

Correct : C. Risk and Impact Matrix

50. During which stage of Risk planning are modeling techniques used to determine overall effects of risks on project objectives for high probability, high impact risks?

Correct : D. Perform Quantitative risk analysis

51. Supplier risk is highest with ___________.

Correct : C. Firm fixed price contract.

52. You have just completed Qualitative Risk Analysis of the project. What should you be doing next?

Correct : B. Perform Quantitative Risk Analysis

53. Risk Management Plan may include

Correct : A. Budgeting, Timing, Thresholds, Methodology

54. Reserve analysis is NOT a Tool/Technique in which of the following processes?

Correct : D. Activity Resource Estimation

55. Which of the following is not a tool or technique used during the Risk Quantification Process?

Correct : B. Contingency planning

56. Risk management is responsibility of the

Correct : D. Project team

57. What is associated with product risk?

Correct : D. Test object

58. A ____________ is a temporary endeavor undertaken to create a unique product service or result.

Correct : D. Project

59. Assembling project team and assigning their responsibilities are done during which phase of a project management?

Correct : A. Initiation

60. The basic nature of a project is a/an _____ one.

Correct : B. temporary

61. The structure of a project will vary depending on the _________to provide.

Correct : A. benefits it is intended

62. A process that involves continuously improving and detailing a plan as more detail become available is termed as

Correct : D. progressive elaboration

63. A program is usually a group of

Correct : C. related projects

64. Which from the following statement(s) is/are NOT true? I. Projects have defined objectives II. Programs have a larger scope than projects III. The projects and programs in a portfolio must be directly related

Correct : C. III only

65. Projects management is divided in _____ process groups.

Correct : A. 5

66. ____________are avoided by providing more tangible and objective results troughout the life cycle.

Correct : A. Adversarial stakeholder relationship

67. .If any one factor of a project changes, _____ other factor(s) is/are likely to be affected.

Correct : C. at least one

68. Business Value =

Correct : D. Tangible Elements + Intangible Elements

69. Which from the following is NOT a tangible element?

Correct : B. Trademarks

70. A horizontal bar chart that shows project tasks against a calendar is called

Correct : C. Gantt chart

71. Which from the following represents the correct project cycle?

Correct : C. Initiating→Planning→Executing→Closing

72. The strategy used to correct resource over-allocations by balancing demand for resources and the available supply is known as

Correct : B. resource leveling

73. The statistical tool that depicts a project’s tasks and the relationships between those tasks is known as

Correct : D. PERT chart

74. Which of the following is NOT a part of project management?

Correct : D. All above are parts

75. The scope of the work is defined in which phase of the project management?

Correct : A. Initiating

76. How the project work will be carried out, monitored, and controlled? These questions are answered in which phase of the project management?

Correct : B. Planning

77. The review of the successes and the mistakes is normally held during _____ phase.

Correct : D. closure

78. The business case and the justification for the project is determined during the _____ phase.

Correct : A. initiation

79. According to Olivier Mesly, the 4 P’s critical for the success of a project are:

Correct : B. plan, processes, people, power

80. Developing a technology is an example of

Correct : B. Project

81. The project life cycle consists of

Correct : D. All of the above

82. Following is(are) the responsibility(ies) of the project manager.

Correct : D. All of the above

83. Following are the phases of Project Management Life Cycle. Arrange them in correct order Design, 2. Marketing, 3. Analysis and evaluation, 4. Inspection, testing and delivery

Correct : A. 3-2-1-4

84. Design phase consist of

Correct : C. Both (A) and (B)

85. Project performance consists of

Correct : D. All of the above

86. Five dimensions that must be managed on a project

Correct : B. Features, Quality, Cost, Schedule, Staff

87. Resorce requirement in project becomes constant while the project is in its _____ progress stage.

Correct : D. 80 to 95%

88. The probability of completing the project can be estimated based upon the ____ .

Correct : B. Normal distribution curve.

89. In the initial stage of the project the probability of completing the project is ___ .

Correct : C. Low

90. Each component of the software product is separately estimated and the results aggregated to produce an estimate for the overall job.

Correct : C. Bottom-up

91. Following is (are) the component(s) of risk management

Correct : D. All of the above

92. Following are the characteristics of Project Mindset.

Correct : A. Time, Responsiveness, Information sharing, Processes, structured planning

93. “Devising and maintaining a workable scheme to accomplish the business need” is

Correct : B. Planning process

94. Which one of the following is not an attribute of a project?

Correct : B. Has no definite end date

95. Which one of the following is not a characteristic of a Project?

Correct : B. Familiarity

96. _________comprehensive and flexible system for achieving, sustaining and maximizing business success

Correct : C. Six Sigma

97. Which of the following is responsible for the quality of the project deliverables?

Correct : B. The project team

98. Which of the following is an example of internal failure cost?

Correct : A. Rework

99. QC is typically a(n) _______________ process.

Correct : D. Inspection

100. In quality management, which of the following is not an attribute of the cost of nonconformance?

Correct : C. Safety measures