1. Zero duration activities but are assumed to start at the same time as the
first and the end at the same time as the last one is called__________ activity.
Correct : C. hammocked.
2. ……………..is called if subsequent have the time by which an activity may be
delayed without affecting.
Correct : C. free float
3. _________ activities on the network diagram have zero duration and use
no resources.
Correct : B. dummy.
4. ____________is part of Risk Management.
Correct : D. risk control, planning, identification and monitoring.
5. The activities have zero duration but are assumed to start at the same
time as the first and the end at the same time as the last one is
called__________ activity.
Correct : C. hammocked.
6. ____ is carried out to calculate the earliest dates on which each activity
may be started and completed.
Correct : B. forward pass.
7. In Software Prototype, ___________ means copies of input screens are
shown to the users on a workstation, but the screens cannot actually be used.
Correct : C. mock-ups.
8. . In software prototype, partial working model is classified into ________.
Correct : A. vertical and horizontal.
9. . The scope of the deliverables for an increment is rigidly constrained by an
agreed deadline called as ____________.
Correct : B. time boxing.
10. . SSADM means ___________.
Correct : B. structured systems analysis design method.
11. Sometimes redesigns of the code is often called as ________.
Correct : A. refactoring.
12. Find the two levels of development suggested by Booch ?
Correct : A. micro and macro processes.
13. ________ is refined by Barry Boehm and his co-workers.
Correct : B. cocomo iv.
14. CPM can be expanded as _______.
Correct : B. critical path method.
15. he Cost Benefit Analysis is done for ___________ feasibility.
Correct : D. economical.
16. One can_______ is classified into Functional and Non-functional.
Correct : B. requirements.
17. Security (backups, firewall) will be a ________ requirement.
Correct : B. non-functional.
18. Time behaviour is the sub-characteristics of _______.
Correct : B. efficiency.
19. ________ a set of attributes (data items) and that will be manipulated
within the software (system).
Correct : C. object.
20. _________ indicates the connectedness of the system that can be derived
mechanically.
Correct : D. relationship.
21. Diagrammatic form for Flow oriented Modelling………