Quiznetik

Cost Accounting | Set 3

1. When the completion stage of a contract is less than ¼, the total expenditure on the contract is transferred to ………………..account.

Correct : A. Work-in-Progress

2. If the amount of work certified is less than………of the contract price, then no profit should be taken to Profit & Loss Account.

Correct : B. 25%

3. Contract costing is not used in one of the following industries.

Correct : C. Automobiles

4. The sum of value of work certified and uncertified appearing in the Contract Account is called ……………..

Correct : A. Work in Progress

5. ……………………is the most suitable method in a transport industry.

Correct : B. Service costing

6. Room/day is the cost unit used in…………………

Correct : A. Hotels

7. Maintenance charges are in the nature of …………………expenses.

Correct : C. semi-variable

8. In transport costing………………charges vary more or less in direct proportion to kilometers run.

Correct : A. Running

9. Service costing is called as ……………….

Correct : B. Operating costing

10. In electricity supply company uses …………….as cost unit.

Correct : A. Kilo watt hour

11. In transportation costing a composite unit such as …………….is used.

Correct : A. passenger mile/km or Ten kilometer

12. Boiler house costing is an example of …………….costing

Correct : C. service

13. In service costing, fixed charges are also called as…………………..

Correct : A. Standing charges

14. Service costing is not used in one of the following:

Correct : D. Electronics

15. If the present cost of the car is Rs.1,00,000 residual value at the end of the 5th year is Rs.20,000, the monthly depreciation is…………

Correct : C. Rs.1,333

16. A bus carries 25 passengers daily for 25 days and its mileage per month is 1000 kms. Its passenger miles are………………

Correct : D. 25,000

17. In ……………………costing where standardized goods or services result from a sequence of repetitive and more or less continuous operations to which costs are collected and averaged over the units produced during the year:

Correct : C. Operation

18. The method of costing applied in biscuit industries is ………….costing and in steel industry………….costing.

Correct : A. Job, process

19. Average unit cost for each process is calculated by dividing the ………………..by…………………

Correct : B. total process cost, number of units in process

20. Where raw material is to pass certain stages, before it is converted into finished goods, the method of costing used is…………………

Correct : C. Process Costing

21. When the actual loss is more than the estimated loss, the difference between the two is considered to be………..

Correct : A. Abnormal loss

22. When actual loss is less than the estimated loss, the difference between the two is considered to be……………

Correct : A. Abnormal gain

23. When actual loss is ………..than the estimated loss, the difference between the two is considered to be abnormal gain

Correct : B. less

24. When actual loss is ………………than the estimated loss, the difference between the two is considered to be abnormal loss.

Correct : A. More

25. When 1000 units are 60% complete in a process, it is equivalent to …………….completed units.

Correct : B. 600

26. Equivalent units represent the production of a process in terms of ………..units.

Correct : A. Completed

27. …………..process loss should be transferred to costing profit & loss account.

Correct : A. Abnormal

28. The cost of …………..process loss is absorbed in the cost of production of good units.

Correct : B. normal

29. In inter process profits, the output of one process is transferred from one process to another not at …………….but at ……………….

Correct : B. Actual cost, market price

30. Where actual loss in a process is less than the anticipated loss, the difference between the two is considered to be ………………..

Correct : C. abnormal gain

31. In process costing, the abnormal loss is treated as ……….cost and written off to profit & loss account.

Correct : B. period

32. The process costing is not used in one of the following.

Correct : C. cement

33. ………….arises where the actual process loss is less than the normal predetermined process loss.

Correct : C. abnormal gain

34. An input of 5000kg of material introduced into the process and the expected loss is 8% and if the actual output from the process is 4300, the abnormal loss is …………kg

Correct : B. 300

35. Budgeting system……………key managerial functions.

Correct : B. integrates

36. …………………is a budget which is updated continuously by adding a further period (a month/quarter) and deducting a corresponding earlier period.

Correct : D. both a & b

37. The budget relating to ………….must be prepared first and the other budgets should be prepared in the light of that factor.

Correct : A. Limiting factor

38. …………………budget is the most important budget and it forms the basis on which all the other budgets are built up.

Correct : D. sales

39. ………………….budget may be classified into material cost budget, labour cost budget and overhead budget.

Correct : A. Cost of Production

40. ……………….budget gives an estimate of the anticipated receipts and payment of cash during the budget period.

Correct : C. Cash

41. ……………….is the consolidated summary of the various functional budgets.

Correct : A. Master Budget

42. …………………budget is designed to remain unchanged irrespective of the volume of output or turnover attained.

Correct : B. Fixed

43. …………………budget gives differentbudgeted costs for different levels of activity.

Correct : C. Flexible

44. …………………budget is the preparation of budget starting from a clean state.

Correct : B. Zero Base

45. Calendar Ratio =

Correct : A. Number of actual working days in a period x 100 Number of working days in the budget period

46. Capacity Ratio =

Correct : B. Actual hours worked x 100 Budgeted hours

47. Efficiency Ratio=

Correct : C. Standard hours for actual production x 100 Actual hours worked

48. Activity Ratio =

Correct : D. Standard hours for actual productionx 100

49. ……………….is a summary of all function budgets in a Capsule form.

Correct : A. Master Budget

50. ……………..determines the priorities of functional budget.

Correct : C. both a & b

51. Cash Budget is a ……………….budget.

Correct : C. short term

52. The primary difference between a fixed budget and a variable(flexible) budget is that a fixed budget:

Correct : D. Is a plan for a single level of sales(or other measure of activity), while a variable budget consists of several plans, one for each of several levels of sales (or other measure of activity)

53. Sales budget is a

Correct : A. Functional budget

54. In the case of plant, the limiting factor may be:

Correct : A. Insufficient capacity

55. The difference between fixed and variable cost has a special significance in the preparation of

Correct : A. Flexible budget

56. The budget that is prepared first of all is…………..

Correct : C. budget for the key factor

57. In case of materials the key factor may be.

Correct : B. restrictions imposed by quota

58. The budget which commonly takes the form of budgeted profit and loss account and balance sheet is

Correct : B. master budget

59. Standard cost is a …………..cost

Correct : A. Predetermined

60. The limitations of …………………………has led to the development of standard costing system.

Correct : A. Historical costing system

61. Standard costing is more widely applied in…………………industries.

Correct : A. Process and engineering

62. Three types of standards are…………..

Correct : A. Current standard, basic standard and normal standard

63. The deviation of the actual cost or profit or sales from the standard cost or profit or sale is known as …………

Correct : B. Variance

64. Management by exception is exercising control over………..

Correct : C. Unfavourable items

65. Material price variance is the difference between standard and actual prices of materials used multiplied by………………..

Correct : A. Actual quantity of materials used

66. Labour cost variance is the difference between standard cost of labour and………..

Correct : C. Actual cost of labour

67. Idle time variance is………….

Correct : B. Idle time x standard rate

68. Volume variance is divided into……………

Correct : B. Capacity variance, calendar variance and efficiency variance

69. Standards set provide yardsticks against which………….are compared.

Correct : C. Actual costs

70. The technique of standard costing may not be applicable in case of

Correct : D. Both b & c

71. Total Material cost variance =

Correct : A. Standard cost of materials-actual cost of materials

72. Material Usage Variance=Material Mix Variance +…………..

Correct : A. Material Yield Variance

73. Material Price Variance = Actual Usage (……………)

Correct : B. Standard unit price-actual unit price

74. Material usage variance = standard price(……………….)

Correct : A. Standard usage-actual usage

75. Material mix variance = standard cost of standard mix - ………………..

Correct : C. Standard cost of actual mix

76. Total Labour cost variance =

Correct : A. Standard cost of labour - actual cost of labour

77. Volume Variance =

Correct : D. All of the above

78. A favourable variance will arise when capital revenues are………..than expected.

Correct : A. More

79. An unfavourable material price variance occurs because of:

Correct : A. Price increase in raw materials

80. The type of standard best suitable for cost control purpose is

Correct : D. Expected standard

81. An unfavourable material usage arises because of:

Correct : D. More than anticipated normal wastage in the manufacturing process

82. Volume variance arises because of :

Correct : C. Increase or decrease in actual output as compared to the budgeted output.

83. Labour rate variance is computed by multiplying the

Correct : D. None of the above

84. ……………..is an example of long-term budget

Correct : D. Both b & c

85. ……………..is an example of short-term budget

Correct : D. Both a & c

86. The main objective of cost accounting is:

Correct : D. All of the above

87. The expected return or benefit foregone in rejecting one course of action for the other is known as

Correct : B. opportunity cost

88. Costs which are ascertained after they have been incurred are called

Correct : C. historical costs

89. A cost centre is

Correct : A. a production or service location, function, activity or item of equipment whose costs may be attributed to cost units

90. These accounts are obligatory to be prepared according to the legal requirements of Companies Act and Income Tax Act.

Correct : B. Financial Accounting

91. The cost unit for a cement industry is

Correct : C. Tonne

92. Hypothetical costs which are specially computed outside the accounting system for the purpose of decision making are called

Correct : B. Imputed Cost

93. Direct material + Directlabour + direct expenses =

Correct : A. Prime Cost

94. Costing is a technique of ascertaining: -

Correct : A. Cost

95. The cost can be controlled by:

Correct : D. All of these

96. It is a device for the purpose of breaking up cost into smaller sub-divisions:-

Correct : A. Cost Unit

97. Elements of cost are:-

Correct : D. All of thesew

98. These types of costs are partly fixed & partly variable is relation to output:-

Correct : C. Semi-variable Cost

99. Cost accounting has been developed because of limitation in:-

Correct : A. Financial a/c

100. The cost which is to be incurred even when a business unit is closed is a ____ cost.

Correct : D. Shutdown